Current Stellar Updates - Autumn/Winter 2015 PDF Print E-mail
Downtown Construction Updates
Click here for a map showing 2016 downtown projects and construction areas. NEW - UPDATED MAP for 2016!

2016 Completed Downtown Projects
  • Facades: The construction of downtown facades is now complete.
  • Delphi Opera House: Restoration of the Delphi Opera House is now complete. Program information can be found at http://www.delphioperahouse.org/
  • Water Mains: Construction of new downtown water mains and services is now complete.
Streetscape Project
Streetscape work has been awarded to Milestone Contractors. Work for 2015 is expected to wrap up in November. In the Spring of 2016, the contractor will continue the streetscape improvements in the balance of the downtown including work on Franklin, Market, Main and South Washington Streets. Final repaving of the streets is scheduled for late 2016, although it is possible it could take until early 2017.

Weekly informational meetings on the project will resume in the Spring when work resumes.

Owner Occupied Housing
The city will be moving forward with the second phase of the Owner Occupied Housing project in early 2016. More details will be announced soon.

Gateway Trail Phase 2
Bids have been received for the second phase of the Gateway Trail. Contracts have been awarded to Milestone Contractors. Some clearing, preparation and wall construction work may occur over the winter. But, the bulk of the project will be constructed in the spring. Work areas include Washington Street from Monroe Street to Columbia Street, and from Front Street to Summit Street.

To review concept materials and detailed summaries on the various projects, click here.